Modernization of boiler houses
Gas boilers and auxiliary equipment
| Name of the project and period of its implementation | Gas boilers and auxiliary equipment HORISHNI PLAVNI Centralized heat supply project – Increasing the energy efficiency of the centralized heat supply system in the city of Horishni Plavni Participation in the DSD: LLC PKP KOTLOGAZ (Ukraine), KOMENERGOSERVICE (Ukraine), KOMFORTS (Latvia) 2019 term of the contract – 9 months |
| Program name (MFI), project amount | Credit received from NEFCO (Nordic Environment Finance Corporation) 4,998,655 euro |
| Technical description | Phase 1 includes:
Phase 2 includes:
All deliveries and installation of equipment were carried out in the existing main boiler house on the street. Energetikov, 31 in the city of Horishni Plavni |
Modernization (reconstruction) of the boiler room
| Name of the project and period of its implementation | Modernization (reconstruction) of the RK-8 boiler house at the address: 22 Myru Avenue Zhytomyr February 2018 – December 2019 |
| Program name (MFI), project amount | EBRD (European Bank for Reconstruction and Development) 643 271 euro |
| The main stages of the implementation of this project are the supply of modern equipment, carrying out a complex of works on the modernization of 2 existing boilers of the DKVr 10-13 type, with a total capacity of 18 MW, and one DKVr 10-13 boiler , with a capacity of 8 MW (installation, inspection, testing), commissioning and commissioning of the facility. The boiler house has the following new equipment:
Performed installation work:
Works have also been completed on replacement of external and internal pipes of the heating network with a device for removing dirt; level system of automatic signaling of the boiler room; feeding tank for water storage (V = 25 m3) |
Replacement of boilers
| Name of the project and periodof its implementation | Replacement of NIISTU-5 boilers at the boiler house on the street Dombrovskyi, 30 Zhytomyr July 2014 – March 2015 |
| Program name (MFI), project amount | NEFCO (Nordic Environment Finance Corporation) 328,400 euro |
| Technical description | The NIISTU-5 boilers were replaced with 2 new Riello TAU 800N water-heating gas condensing boilers, with a capacity of 800 kW each, with the installation of 2 Riello RS 120/EV BLU burners on the boilers; also established:
|
Supply of gas boilers for the modernization of the boiler room
| Name of the project and period of its implementation | Supply of gas boilers for the modernization of the boiler room on Zulinsky str., 9th VINNYTSIA March 2017 – December 2018 |
| Program name (MFI), project amount | SECO (State Secretariat for Economic Affairs) 572,565 euro |
| Technical description | During the modernization of the boiler room, new equipment was delivered and installed: Viessmann gas boilers in the amount of 3 units, with a total capacity of 13.5 MW; smoke pipes in the amount of 3 units. and gas pipelines; gas supply system and electrical equipment; Wilo pumping station, BWT chemical water treatment system; software package of the SCADA system |
Replacement of circulation pumps and fans
| Name of the project and period of its implementation | Replacement of circulation pumps and fans – Supply and installation of equipment in Berdychiv BERDYCHIV July 2021 – December 2021 |
| Program name (MFI), project amount | NEFCO (Nordic Environmental Finance Corporation) 416,097euro |
| Technical description | The purpose of the implementation of this project is to modernize the thermal equipment of the boiler houses of the centralized heat supply system in the city of Berdychiv. The project provided for the supply and installation of circulation pumps (including electric motors), smoke extractors and boiler fans at 11 existing boiler houses of the city. The total amount of installed equipment is: The power of circulation pump motors min – 11 kW, max – 110 kW. The set of completed works on the project included: |
Installation of individual thermal points
| Name of the project and period of its implementation |
Installation of individual heat points (8 units), incl. insulation of pipelines, fittings, elements of the heating point, decoration of premises and connection of communications, balancing of heating systems, instead of installed heating units in elementary school No. 15 (new and old school), elementary school No. 22, elementary school No. 25, elementary school No. 28, music school No. 2 , children’s educational institution No. 33, Department of Urban Planning and Architecture Rivne January 2022 – November 2023 |
| Program name (MFI), project amount |
NEFCO (Nordic Environmental Finance Corporation) 276,441 euro |
| Technical description |
The project was carried out in connection with the reconstruction of the individual heating points (ITP) of the objects specified in the project in the city of Rivne and in accordance with the program for the implementation of energy saving in establishments and institutions belonging to communal property of Rivne. The source of heat supply is local heat networks. The project implemented work on replacing the existing heating system with the use of modern equipment. A weather-dependent control system has been implemented. The heating system is connected to the heat networks according to a dependent scheme with circulation and mixing pumps on the return pipeline of the internal system. Pumping equipment with built-in frequency regulation is installed. Load on the heating system: including: |
Replacement of condensation feed pumps
| Name of the project and periodof its implementation | Replacement of condensation feed pumps in the “Pivdenna” boiler house, Pershotravenska, DNIPROPETROVSKA OBL. December 2017 – July 2018 |
| Program name (MFI), project amount | NEFCO (Nordic Environment Finance Corporation) 59,063 euro |
| Technical description | Purchased and installed Grundfos NK50-160/167A1F2AE-SBQQE condensing pumps in the amount of 2 units, a booster pumping station based on 2 Grundfos CR-45-11-2 pumps A-F-A-E- HQQE with control panel with IF and PP Technical characteristics of the condensation pump:
Technical characteristics of feeding pumps:
|
Installation of new and modernization of existing IHP equipment
| Name of the project and periodof its implementation | Installation of new and modernization of existing equipment 20 IHP, balancing and flushing of internal heating systems, thermal insulation of pipelines and installation of heat energy metering devices in public sector institutions (schools, gymnasiums , department of the central clinical hospital, children’s educational institution) Zhytomyr January 2017 – December 2018 |
| Program name (MFI), project amount | NEFCO (Nordic Environment Finance Corporation) 350 450 euro |
| Technical description |
|
Reconstruction of engineering entrances of multi-apartment residential buildings
| Name of the project and period of its implementation | Reconstruction of engineering inlets of multi-apartment residential buildings with installation of thermal energy metering devices KHERSON December 2016 – December 2018 |
| Program name (MFI), project amount | UDHEEP (Project to improve energy efficiency in the district heating sector of Ukraine) 615,231 euro |
| Technical description | As part of the project “Improving energy efficiency in the district heating sector in Ukraine”, the project “Reconstruction of engineering entrances of multi-apartment buildings with the installation of heat energy metering devices and the purchase of an installation for checking heat energy metering devices in the city of Kherson” was replaced 140 units of thermal energy accounting at the facilities. The installed control and data collection system (SСADA) allowed the Customer to remotely control energy use by consumers in automatic mode. |



